Which of the following tasks will not be done by the processes in the planning process group?

A) Define and refine objectives    
B) Plan the course of action required to attain the objectives.    
C) Identify the project scope    
D) Integrate people and other resources to carry out the project management plan for the project

------------------------------
Hint: What is the function of the Direct and Manage Project Work process?
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at   http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at   http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.


Answer and Explanation:
The Correct Answer is D. Integrating resources is the task of the Direct and Manage Project Work process that belongs to the executing process group.

Until Next Time,

Cornelius Fichtner, PMP

President, OSP International LLC

Views: 64

Comment

You need to be a member of Project Managers to add comments!

Join Project Managers

© 2018   Created by Mike.   Powered by

Badges  |  Report an Issue  |  Terms of Service