The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

Which of the following statements regarding WBS templates is incorrect?

A.) They are always present in Organizational Process Assets.
B.) They provide a starting point for WBS creation.
C.) They may help determine the appropriate level of detail required.
D.) They enhance cross-project WBS consistency.

------------------------------
Hint: WBS templates can help you create your project WBS.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: WBS Templates can be found in Organizational Process Assets but we cannot say they will always be available.
Reference: PMI Practice Standard for WBS 2nd Edition, page 29